Project Updates
Project Update 11/13/2023
As we gear up for winter’s arrival, our top priority is closing up the Moana Springs Aquatic & Fitness Center. If you happen to stroll by, you can’t miss the large strides we’ve made this month. The natatorium spaces have received almost all of the 70 precast concrete panels that will wrap and insulate the building. Some of these hefty panels tip the scales at over 20,000 pounds, demanding the skillful touch of our fantastic building partners. In addition, our exterior framing is racing toward the finish line, and the interior framing is making steady headway. With framing nearly done and our precast walls firmly in place, it’s time to start measuring and installing the glass to seal up the building. Wrapping up the building façade just as Winter knocks on our door is no walk in the park, but it’s absolutely vital to keep the momentum going strong throughout the season.
Project Update 10/11/2023
The construction of the Moana Springs Aquatic & Fitness Center is proceeding smoothly. Since our last update, we have completed all perimeter concrete work, with only the pool decks remaining to be finished. As we enter October, one of the project’s most exciting phases is about to begin: the excavation of the pools. While the pool excavation is underway, construction in the central area of the building (including the lobby, locker rooms, restrooms, showers, and recreation room) will continue to make significant progress with framing, mechanical, plumbing, and electrical system installation.
Project Update 8/1/2023
Construction of the Moana Springs Community Aquatics & Fitness Center is well underway. The reception and locker room areas are starting to take shape with utility tie-ins and a concrete pad ready to accept framing and be overlayed with flooring. Sub-grade concrete pits that will provide the mechanical heartbeat for operation of the pools have also been constructed. This portion of construction sets the stage for erection of the steel mainframe which began mid July and will continue into early August. Once the steel mainframe is squared and true, precast concrete panels will be installed to provide modern aesthetics. Moving forward, construction will be fast paced. We look forward to the near future, as vertical construction complements the shape of the future Moana Springs facility.
Project Update 06/5/2023
Over the past few weeks, CORE’s trade partners have made great strides installing the building’s underground utilities. So far we have roughed-in much of the underground plumbing as we finish pouring the last foundation elements. This week, we are very excited to kick off trenching for the pool’s utilities as the pool contractor joins the team on site. With all this underground work underway, our team is eager to go vertical and bring this structure to life. Currently, we expect to see steel on-site at the beginning of July, with erection of the structure to follow just a couple weeks later.
Project Update 05/1/2023
The building permit for the Moana Springs Community Aquatics and Fitness Center has been approved. Construction is really ramping up on the project as building layout and excavation are well underway, opening the door for various trades to begin acclimating themselves to the jobsite. CORE is currently charting and excavating the building’s footings and will soon begin to pour concrete for the steel structure with steel erection and underground utilities to follow. We are thrilled to get started and provide more updates in the coming months!
Project Update 03/20/2023
Following a brief break due to weather restrictions, construction has resumed on the Moana Springs Community Aquatics and Fitness Center! CORE has managed to complete a few important items over the last few month despite the snowy conditions. Most notable was the construction of the enclosure for the NV Energy transformer and the completion of underground BIM coordination efforts. CORE is currently gearing up for excavation and preparation of the building’s pad after approval of the building permit. This signifies a large milestone in construction as it commences the start of the building’s foundation.
Keep an eye out in the coming weeks and months as site traffic picks up and the structure begins to take shape. Our team is very excited for the oncoming warm weather and, ultimately, the next phase of construction.
Project Update 11/18/2022
Construction of the Moana Springs Community Aquatics and Fitness Center project continues into autumn with site work that includes utility work, concrete placement and paving. Traffic control has been removed from Moana Lane opening up vehicle travel to both east bound lanes and pedestrian travel to new sidewalks, curb, gutter and driveway. Traffic control will continue on Baker Lane through winter to establish new utility services. Parking lot work continues with construction of interior sidewalks, and light pole foundations.
Project Update 09/26/2022
Construction of the Moana Springs Community Aquatics and Fitness Center project kicked off with site demolition and earthwork. Site demolition was completed in September with removal of the salt and sand shed, playground equipment, asphalt and concrete pavement, and some turf. Traffic control measures were setup on W Moana and Baker Lanes to provide the construction crews access to gas, electric, water, storm drain, and sewer utilities that are located under the roadway. New connections to the utilities are required to service the new facility. New sidewalks and driveways will be constructed after the utility connections are completed. The traffic control measures are expected to be removed October 2022. Earthwork is ongoing and will continue with grading the soil for the new parking lots and excavation for the new building foundation and pools. A live Project Webcam is now included on the Project Updates page on the MoanaSprings.com website.
Re-Know Minute Featuring Moana Springs Community Aquatics and Fitness Center
